Construction ERP in Quebec: what it needs to handle in 2026

A construction ERP tracks the cost of every job, subcontractors, payment applications, holdbacks and the CCQ monthly report. Here is what Quebec requires.

, co-founder of Cogio

A foreman speaks into a two-way radio next to a colleague checking a tablet on a construction site
Photo: Mikael Blomkvist, Pexels

What a construction ERP does beyond accounting software

Accounting software answers one question: how much did the company make this month? A construction ERP also answers the question every project manager asks: how much has this job cost so far, and how much is left to bill? To get there, it ties every purchase, every subcontractor invoice and every hour worked to the right job, as they happen.

An ERP, or enterprise resource planning system, brings accounting, purchasing, sales and project tracking together in one database. In construction, seven functions set it apart from accounting software.

  • Job costing. Materials, labour, equipment rental and subcontracting are charged to the job and its cost code, then compared with the budget from the quote.
  • Quotes. The estimate becomes the job budget as soon as the contract is signed, with no re-entry.
  • Purchase orders. Every purchase carries the job number. The supplier invoice is matched to the purchase order and the receipt.
  • Subcontractors. The contract, the RBQ licence, the Attestation de Revenu Québec, invoices, holdbacks and releases all live in a single record.
  • Payment applications. Progress billing is built from the work completed, with the breakdown the owner requires.
  • Holdbacks. The ones applied to you and the ones you apply are tracked until they are released.
  • Hours by job. Each hour is entered once, by worker, trade and job. It feeds payroll, job costing and the monthly report to the CCQ.

Job costing, at the heart of the system

Take a mechanical contractor in Sherbrooke running six jobs at once, including an addition to an elementary school. At month end, the accountant knows what the company paid. The project manager wants to know whether the school job is on budget while there is still time to act.

The ERP answers in real time. The purchase order for the pipe carries the job number and the supplier invoice is matched to it as soon as it arrives. The pipefitters’ hours are entered on that job every day. Committed costs are compared with the quote budget, line by line. Variances show up along the way rather than on the final invoice.

The same link also prepares the month’s payment application, the price of extra work and the contract’s actual margin. The school’s actual costs then become the reference for the next comparable quote. Our article on construction quotes shows how an agent puts them to use.

Les Industries Romy, which fabricates and installs steel structures in Granby, started from this exact problem. Its case study describes the starting point as “labour and material costs not tracked per project: no way to know the total spend on a job.” Today, supplier invoices arrive by email, are read by an agent, matched to the project and written into QuickBooks through its API. Job costing builds up as the work happens rather than at month end. Robin Langlois, owner of Les Industries Romy, is also a co-founder of Cogio. The details are in the Romy case study.

The Quebec deadlines a construction ERP has to track

In Quebec, much of a job’s administration follows dates set by law. The table brings together the main ones and what an ERP or an agent can prepare for each. The sections that follow give the details and cite the provisions. For a specific file, your contract and your legal advisor remain the reference.

The main deadlines for a construction contractor in Quebec
Monthly report to the CCQ and payment of amounts dueEvery employer subject to Act R-20By the 15th, for the previous monthly periodHours by worker, trade, sector and job, ready for payroll
Copy of a subcontractor’s Attestation de Revenu QuébecThe subcontractor provides it, the contractor obtains it and checks that it is validBy the 7th day after work startsThe request as soon as the subcontract is signed, then reminders
Verification of the attestation’s authenticityThe contractorBy the 10th day after work startsA reminder to the person responsible and the verification date on file
Subcontractor’s request for payment (covered public contract)The subcontractorBy the 25th of the monthThe request built from work completed, with the required breakdown
General contractor’s request for payment (covered public contract)The general contractorThe 1st of the monthThe request showing each subcontractor’s share in dollars
Notice of refusal to pay (covered public contract)The public body or the general contractorBy the 21st (public body) or the last day of the month (general contractor)The written notice with reasons, ready to review
Payment of subcontractors (covered public contract)The general contractorBy the 5th of the second month after the month their request was receivedThe payment schedule and follow-ups
Final acquittances from subcontractors (covered public contract)The general contractorBy the 25th of the month in which the final request for payment is receivedThe list of acquittances and the CNESST confirmation to obtain, with follow-ups
Statement of amounts paid and owed to subcontractors (private contract with progress payments)The contractorBefore each progress paymentThe statement drawn from the job’s accounts payable
Notice preserving the legal construction hypothecThe unpaid creditor (subcontractor, supplier, contractor)Within 30 days after the work is completedThe completion date and the amounts still owed

The monthly report to the CCQ

Every employer subject to Act R-20 sends a monthly report to the Commission de la construction du Québec. The deadline is set by section 12 of the Regulation respecting the register, monthly report, notices from employers and the designation of a representative: no later than the 15th of each month, for the previous monthly period, which ends on the last Saturday of the month. Amounts due are paid by the same date (section 13). A month with no work at all still requires a notice of inactivity.

For each worker, the report shows their trade, regular and overtime hours, region, sector, wages paid and contributions (section 11). For late filing, the CCQ applies a penalty of 7% of the amount due for up to 7 days, 11% for up to 14 days and 20% beyond that, plus daily interest.

The report is filed through the CCQ’s online services, through authorized accounting software or a payroll service provider, or by uploading a JSON file. For an ERP, the real work happens upstream: if each hour is entered once, by worker, trade, sector and job, the report can be prepared without re-entry. An agent can gather those hours every week and flag anomalies, such as a worker logged on two jobs at the same hour. The person who runs payroll reviews, then submits.

The Attestation de Revenu Québec for subcontractors

A construction contract signed since March 1, 2016, between a contractor and a subcontractor requires the Attestation de Revenu Québec when the work calls for an RBQ licence and the contract reaches $25,000 before taxes, alone or added to the contracts the same parties have already signed in the calendar year. Once that threshold is crossed, all their later contracts are covered, whatever the amount.

Two dates matter, counted from the start of work (Taxation Act, sections 1079.8.17 and 1079.8.18). By the 7th day, the subcontractor provides a copy of its attestation and the contractor makes sure it is valid: right name, right address, validity period not expired. By the 10th day, the contractor verifies its authenticity in Revenu Québec’s My Account for businesses. These obligations apply at every level of subcontracting.

An attestation remains valid until the end of the third month after the month in which it was issued (section 1079.8.19). Penalties range from $250 to $5,000 depending on the failure, including when the contractor pays a subcontractor without having corrected the situation (section 1079.8.21). They apply only after the minister has already sent a notice by registered mail (section 1079.8.23).

This is a job made for an agent. When the subcontract is created, it calculates the year’s total with that subcontractor, requests the attestation if the threshold is reached, then follows up before the 7th day. It reminds the person responsible to verify it before the 10th. As long as the document is missing, it flags every payment scheduled for that subcontractor so a person can decide.

Prompt payment on public contracts

Quebec’s Regulation respecting prompt payments and the prompt settlement of disputes with regard to construction work (CQLR, c. C-65.1, r. 8.001) has been in force since September 8, 2025. It covers construction contracts awarded by public bodies within the meaning of the Act respecting contracting by public bodies, such as government departments, school service centres, CEGEPs and health institutions, along with their subcontracts.

It applies in stages (section 94). Since September 8, 2025, it has covered building contracts of $750,000 or more and civil engineering contracts of $2.5 million or more. Since September 8, 2026, it also covers building contracts of $75,000 or more and civil engineering contracts of $675,000 or more. On September 8, 2027, it will apply to all contracts. Contracts already under way on those dates, and those resulting from a call for tenders launched before them, are not covered (section 90).

The calendar is fixed. A subcontractor sends its request for payment by the 25th of the month and the general contractor sends its own on the 1st of the month, showing each subcontractor’s share in dollars (section 5). A late request is treated as received the following month, unless the debtor decides to overlook it (section 7). A refusal takes the form of a written notice with reasons, by the 21st for the public body and the last day of the month for the general contractor (sections 10 and 11). The public body pays by the last day of the month in which it receives the request. The general contractor pays its subcontractors by the 5th of the second month after the month their request was received (section 15).

Three rules have a direct impact on the numbers. A change whose value has not yet been agreed is not, on its own, grounds for the public body to refuse payment (section 12). The withholding, or holdback, may not exceed 10% and exists only if the contract provides for it (section 20). For the final payment, the public body may withhold everything until it has the CNESST confirmation and the final acquittances of all subcontractors (section 28).

In an ERP, the regulation becomes a monthly routine. A few days before the deadline, the agent builds the request from the work completed and the job’s costs, with the description of the work, the periods and the breakdown that section 5 requires. At the general contractor, it adds the subcontractors’ requests and calculates the holdbacks. The request must be dated and signed by the contractor’s representative, who reviews it before it goes out. The agent then tracks the refusal and payment dates.

Holdbacks, acquittances and hypothecs on private contracts

Outside public contracts, the Civil Code of Québec sets most of the rules. If the contract provides for progress payments, the contractor must give the client, before each one, a statement of the amounts paid to subcontractors and material suppliers, along with the amounts still owed to them (article 2122).

The client may withhold enough to pay the claims of workers and of other creditors who have given notice of their contract, until the contractor provides an acquittance (article 2123). When accepting the work, the client may also withhold enough to cover reservations about apparent defects or poor workmanship (article 2111). Sufficient security from the contractor removes that right in both cases.

The legal construction hypothec subsists for 30 days after the work is completed, even if it has not been published. To preserve it, the creditor registers a notice before that period ends and serves it on the owner. It is extinguished six months after the work is completed, unless an action is published or a prior notice of the exercise of a hypothecary right is registered (article 2727). Except for workers, anyone who did not contract with the owner is protected only for work supplied after written notice of the contract to the owner (article 2728).

Two other statutes affect the subcontracting chain. Wages owed by a subcontractor are a joint and several obligation shared with the contractor and any intermediary subcontractors. If that subcontractor holds its RBQ licence, the obligation ends six months after its work is completed, unless a complaint or claim is filed before then (section 54 of Act R-20). The CNESST may also require whoever retains a contractor’s services to pay the assessment owed by that contractor (section 316 of the Act respecting industrial accidents and occupational diseases).

An ERP has nothing to invent here: the data is already in the job’s accounts payable. The article 2122 statement is produced when the progress payment is billed, notices received are filed with the job and the agent follows up on expected acquittances until the final payment. None of these tools replaces a lawyer’s advice on a dispute.

What an agent prepares and what a person approves

An AI agent is not one more module. It is software that starts on its own when something happens (the end of a pay week, a signed subcontract, an incoming invoice) and prepares the work in the ERP. An ERP whose agents handle data entry and preparation this way is called an agentic ERP.

The rule is the same for every task: the agent prepares, a person approves anything that commits the business. At Cogio, two workflows are in production at a client: quotes and supplier invoices. Our guide to automating quotes in an SME covers the first. For job-related purchasing, see how to automate purchase orders.

In construction, four other tasks are a good fit. At Cogio, they are configured on request, around your contracts and your tools.

  • The hours report. Every week, the agent gathers hours by worker, trade, sector and job, then hands them to payroll for the CCQ report.
  • The request for payment. Before the 25th or the 1st, it builds the request from work completed and costs. The company’s representative reviews and signs it.
  • Attestation tracking. It requests each subcontractor’s Attestation de Revenu Québec, watches the 7th and 10th days, then flags any payment scheduled for a subcontractor whose file is incomplete.
  • Follow-ups. Late payments, missing acquittances, subcontractor documents: each follow-up is written in your company’s usual tone and saved as a draft.
Animated demo. The drawings are taken off item by item, materials, subcontracting and labour are priced at the company’s rates, then the quote waits for the project manager’s approval.

Types of software for contractors

Contractors generally choose among three types of software. Each has its strengths. The right choice depends on the size of your jobs, how much you subcontract and how much work you do in a shop. Our guide to choosing ERP software in Quebec details the criteria. Licence costs often weigh in the decision: our article on ERP licence costs for an SME runs the numbers.

  • Specialized construction ERPs. They are built around the job: cost codes, progress billing, holdbacks, change orders and subcontracting. They suit general and specialty contractors who run several jobs at once and subcontract a large share of the work. If you want to file the monthly report from your software, check that it is on the CCQ’s list of authorized providers.
  • General ERPs. They cover accounting, purchasing, inventory, manufacturing and project management in a single system. Some offer an edition or modules designed for construction. They suit companies that both fabricate and install, such as a steel structure, window and door or kitchen cabinet shop. Our article on manufacturing ERP covers the shop side.
  • Accounting software and add-on tools. That means QuickBooks, Sage 50 or Acomba, with one spreadsheet for estimates, another for hours and a payroll service. This combination works well for a small team running a few jobs at a time. It holds up as long as someone ties the tools together. As jobs multiply, that link is what takes the most time.

Where to start

With the deadline that costs you the most when it slips. For a roofer in Lévis, it will be the CCQ report rebuilt every month from paper timesheets. For a general contractor in Gatineau, it will be the request for payment on a school service centre contract, put together the day before the 1st. Measure how long the task takes today, hand its preparation to an agent, then compare after a few weeks.

Then choose the path that fits your systems. If you have no ERP, or yours is no longer enough, Cogio offers an ERP with no licence fees and no per-user fees. It includes project management and timesheets. You pay for the services: installation, automations, hosting and maintenance. Payroll stays in your current payroll software. If your ERP works for you, the agents connect to it through its API or its exports, with Acumatica, Business Central, Genius ERP and SAP Business One, among others.

Our examples for general contractors, specialty contractors and subcontractors are on our construction page. For funding, training your team may qualify under MFOR. Since March 13, 2026, the ESSOR program no longer prioritizes construction, except for projects that increase productivity. Quebec programs may be revised after the October 2026 election, so confirm the rates with the agency concerned. Current amounts are on the Funding page, and our article on funding an ERP project covers the options.

To see what a construction ERP with agents would look like in your business, get in touch. We start from your current jobs and the deadline that weighs on you the most.

Frequently asked questions

What is a construction ERP?

Management software that ties every purchase, every hour and every invoice to a job. Along with the company’s accounting, it tracks job costing, quotes, purchase orders, subcontractors, payment applications and holdbacks.

Which management software should a construction contractor in Quebec choose?

It depends on your jobs. A specialized construction ERP suits contractors who run several jobs with a lot of subcontracting. A general ERP suits companies that fabricate and install. Accounting software with a few tools is often enough for a small team. In every case, check how job costing is tracked and how the monthly report to the CCQ will be produced.

When is the CCQ monthly report due?

No later than the 15th of each month, for the previous monthly period. Amounts due are paid by the same date. Late filing brings a penalty of 7%, 11% or 20% depending on the number of days, plus interest.

When do you need a subcontractor’s Attestation de Revenu Québec?

By the 7th day after work starts, for a covered contract. The contractor then verifies its authenticity by the 10th day. The obligation applies once contracts with the same subcontractor reach $25,000 before taxes in the calendar year, for work that requires an RBQ licence.

What are the payment application dates on a Quebec public contract?

For contracts covered by the prompt payment regulation, the subcontractor sends its request by the 25th of the month and the general contractor sends its own on the 1st. Since September 8, 2026, the regulation covers new building contracts of $75,000 or more and civil engineering contracts of $675,000 or more. It will cover all contracts on September 8, 2027.

Can an ERP prepare payment applications automatically?

It can prepare them. An agent builds the request from the work completed and the job’s costs, then tracks the refusal and payment dates. The request is still signed by the contractor’s representative, who reviews it before it goes out.

Sources and references

This article is a plain-language summary, accurate as of the date shown. It is not legal, tax or financial advice: for your own situation, consult a qualified professional.